Project Management Professional (PMP) Practice Exam Flash Cards

Question: 1 / 400

A project manager’s PDM network schedule gets audited by a scheduling expert. The expert tells the project manager to focus more on nodes with “path convergence”, also known as “sinks”. What is the person referring to?

?

Nodes in a network logic diagram which have multiple predecessors.