Project Management Professional (PMP) Practice Exam

Question: 1 / 400

For a project, the following earned value data have been assessed: AC: $4,000,000 CV: $-500,000 SPI: 1.12 BaC: $9,650,000 What is the earned value of the project?

$3,000,000

$3,500,000

The earned value of the project can be derived by adding the actual cost (AC) and the earned value (EV). In this case, the actual cost is $4,000,000 and an unspecified earned value. We can calculate the earned value by subtracting the cost variance (CV) from the actual cost. However, the given CV is -$500,000, which means that the project is over budget. As a result, the earned value must be less than $4,000,000. Option A is incorrect because it is equal to the given actual cost. Option C does not take into account the cost variance and is therefore incorrect. Option D goes beyond the budget at $9,650,000, which is the budget at completion (BaC). The correct answer is B, $3,500,000, which takes into account the cost variance and satisfies the equation EV

Get further explanation with Examzify DeepDiveBeta

$4,480,000

$5,650,000

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy