Project Management Professional (PMP) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Project Management Professional (PMP) exam. Study with flashcards and multiple choice questions. With over 500 questions. Practice the PMP practice multiple choice questions. Updated for 2023-2025. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


A project manager’s PDM network schedule gets audited by a scheduling expert. The expert tells the project manager to focus more on nodes with “path convergence”, also known as “sinks”. What is the person referring to?

  1. Nodes in a WBS, where several branches are brought back together.

  2. Nodes in a conditional network diagram, at which it becomes deterministic.

  3. Nodes in a decision tree, showing various branches with the same chance.

  4. Nodes in a network logic diagram which have multiple predecessors.

The correct answer is: Nodes in a network logic diagram which have multiple predecessors.

The expert is referring to the nodes in a network logic diagram that have multiple predecessors. This means that there are multiple activities or events that need to be completed before the particular node can be reached. It is important for the project manager to focus on these nodes as they can cause delays and impact the overall project schedule. Options A, B, and C are incorrect, as they refer to different types of diagrams and are not specific to the project manager's PDM network schedule.