As the project manager, you decided to arrange a team meeting to identify and analyze lessons learned from quality control with stakeholders. What should you do with them?

  1. Document them and make them part of the historical database for the project and the performing organization.

  2. Discuss them with management and make sure that they remain otherwise confidential

  3. Publish them in the corporate newsletter.

  4. Follow your strategic decisions, independent from lessons learned. These decisions have been made and should be implemented whatever the outcomes are.

The correct answer is: Document them and make them part of the historical database for the project and the performing organization.

Possible explanation It is important for the project manager to document and record the lessons learned from quality control in order to utilize this information for future projects. This data will be valuable for not only this project, but also for the performing organization as a whole. Option B is incorrect because the confidentiality of these lessons should not be compromised. Option C is also incorrect as these lessons are specific to the project and not appropriate for a public newsletter. Option D does not align with the purpose of analyzing lessons learned and using them to improve future projects.