During human resource planning you identified that your team members are not sufficiently qualified for their tasks. Which may be an appropriate solution to this problem?

  1. Reduce level of effort

  2. Develop a training plan

  3. Plan quality audits

  4. Plan quality inspections

The correct answer is: Develop a training plan

Developing a training plan would be an appropriate solution because it would address the issue of team members not being sufficiently qualified for their tasks. Reducing the level of effort would not provide a long-term solution to the problem and may result in a decrease in productivity. Planning quality audits and inspections may help identify areas for improvement, but they do not directly address the qualifications of team members.