Product acceptance criteria should be laid down in which document?

  1. Project scope statement

  2. Work breakdown structure

  3. Resource assignments

  4. Project scope management plan

The correct answer is: Project scope statement

Product acceptance criteria should be laid down in the project scope statement. This document outlines the project's objectives, deliverables, and scope, and sets the standards for determining whether the end product meets the desired requirements. Option B is incorrect because the work breakdown structure focuses on breaking down the project into smaller, manageable components. Option C is incorrect because resource assignments pertain to the allocation of resources to specific tasks, not the acceptance criteria for the end product. Option D is incorrect because the project scope management plan primarily outlines the processes for defining, validating, and controlling the project scope, rather than the specific acceptance criteria for the final product.