The cost baseline is developed during which process?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Study for the Project Management Professional (PMP) exam. Study with flashcards and multiple choice questions. With over 500 questions. Practice the PMP practice multiple choice questions. Updated for 2023-2025. Get ready for your exam!

The cost baseline is developed during the Determine Budget process. This process involves aggregating the estimated costs from the various activities and work packages to establish a cost baseline for measuring project performance. The other options are incorrect because A: Perform integrated change control is responsible for influencing the factors that create project changes and controlling changes to the project's scope, schedule, and costs. B: Estimate costs is responsible for developing an approximation of the monetary resources needed to complete project activities. C: Develop schedule is responsible for analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy