Project Management Professional (PMP) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Project Management Professional (PMP) exam. Study with flashcards and multiple choice questions. With over 500 questions. Practice the PMP practice multiple choice questions. Updated for 2023-2025. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


The cost baseline is developed during which process?

  1. Perform integrated change control

  2. Estimate costs

  3. Develop schedule

  4. Determine budget

The correct answer is: Determine budget

The cost baseline is developed during the Determine Budget process. This process involves aggregating the estimated costs from the various activities and work packages to establish a cost baseline for measuring project performance. The other options are incorrect because A: Perform integrated change control is responsible for influencing the factors that create project changes and controlling changes to the project's scope, schedule, and costs. B: Estimate costs is responsible for developing an approximation of the monetary resources needed to complete project activities. C: Develop schedule is responsible for analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.