The scope baseline includes____.

  1. The various management plans of the project

  2. Schedule baseline and cost baseline

  3. Product configuration ID and statement of work

  4. WBS dictionary, WBS, scope statement

The correct answer is: WBS dictionary, WBS, scope statement

The scope baseline includes the Work Breakdown Structure (WBS), WBS dictionary and scope statement. These three components detail the project's scope and provide a comprehensive breakdown of the work to be completed. Option A is incorrect because the management plans are not included in the scope baseline. Option B is incorrect because while the schedule and cost baselines are important components of project management, they are not included in the scope baseline. Option C is incorrect because the product configuration ID and statement of work are not part of the scope baseline. Option D is the correct answer as it includes all the necessary components for defining and managing project scope.