What are the cost types in modern quality management?

  1. Costs of good quality – costs of bad quality

  2. Planning costs – assurance costs – control costs

  3. Planning costs – doing costs – checking costs – acting costs

  4. Prevention costs – appraisal costs – failure costs

The correct answer is: Prevention costs – appraisal costs – failure costs

Modern quality management typically categorizes costs into four main types prevention costs, appraisal costs, failure costs, and costs of good quality. Option A is incorrect as it only mentions two of these types, without including prevention costs and appraisal costs. Option B and C are not completely inaccurate, as these costs are associated with quality management, however, they are not recognized as the standard types in modern quality management. Therefore, D is the correct answer as it includes all four of the commonly acknowledged cost types in quality management.