What aspect of project management does a change request primarily address?

Study for the Project Management Professional (PMP) exam. Study with flashcards and multiple choice questions. With over 500 questions. Practice the PMP practice multiple choice questions. Updated for 2023-2025. Get ready for your exam!

A change request primarily addresses modifications to project scope, plans, or deliverables because it is a formal document used to propose changes to various aspects of a project. When stakeholders identify a need for a change—whether it's due to new requirements, corrections needed to meet initial specifications, or alterations driven by external factors like market changes—they submit a change request.

This request goes through a defined process for evaluation, which often includes assessing the impact of the proposed change on the project's scope, schedule, cost, and quality. The project manager and team then review the request, considering how it aligns with project objectives and stakeholder needs before reaching a decision.

Resource allocation, quality assurance standards, and team member roles and responsibilities are important elements of project management but are typically part of the broader project management plan rather than the focus of a change request. A change request is specifically aimed at addressing the needs for adjustments in what is being delivered in the project, ensuring that the final output aligns with stakeholders’ expectations and project goals.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy