Which document is developed along the risk management processes from identify risks through plan and implement risk responses to monitor risks?

  1. List of risk triggers

  2. Risk register

  3. Risk mitigation

  4. Decision tree

The correct answer is: Risk register

A List of risk triggers is a document that lists situations or factors that could potentially cause a risk to occur. This document is developed during the "identify risks" process. However, it does not follow through the entire risk management process, which includes implementing risk responses and monitoring risks. Risk mitigation refers to the specific actions taken to reduce the likelihood or impact of identified risks. While mitigation strategies may be included in a risk register, the document itself is not solely focused on mitigation and also includes other information related to the identified risks. A decision tree is a visual tool used for decision making processes, including risk management. Like the risk register, it may be used during the risk management process, but it is not the document that is developed throughout the process. Therefore, the most appropriate and accurate answer is B Risk register. This document is continuously developed and updated throughout the risk management process,