Which of the following documents is not used as input for the validate scope process?

  1. The project management plan, containing the scope baseline consisting of the project scope statement and its associated WBS and WBS dictionary.

  2. The verified deliverables, completed and checked for correctness by the Control quality process.

  3. The requirements traceability matrix, linking requirements to their origin and tracing them throughout the project lifecycle.

  4. The RACI matrix, describing account abilities in case of product rejection.

The correct answer is: The RACI matrix, describing account abilities in case of product rejection.

The RACI matrix is a tool used in the Plan Scope Management process to define roles and responsibilities for managing the project scope. It is not used as input for the Validate Scope process, which focuses on the acceptance of completed deliverables. The project management plan, verified deliverables, and requirements traceability matrix are all used as inputs for the Validate Scope process.