Which process involves managing project changes?

Study for the Project Management Professional (PMP) exam. Study with flashcards and multiple choice questions. With over 500 questions. Practice the PMP practice multiple choice questions. Updated for 2023-2025. Get ready for your exam!

The process that involves managing project changes is Perform Integrated Change Control. This process is a key part of project management, specifically within the Integration Management knowledge area. Its primary purpose is to ensure that all changes to the project scope, schedule, and costs are evaluated, approved, and documented properly.

Perform Integrated Change Control is crucial for maintaining control over the project and ensuring that changes are made in a systematic way. This process includes assessing the impact of changes, obtaining formal approval from stakeholders, and updating project documents and plans to reflect the approved changes. By doing this, project managers can minimize the risks associated with changes and ensure that any alterations contribute positively to achieving project objectives.

Integrating changes effectively allows for better alignment of project deliverables with the stakeholders' expectations and organizational goals, ultimately fostering project success. This process is vital as it helps in maintaining the overall integrity of the project plan even when adjustments are needed.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy