While executing a project, you sense a slightly negative attitude in your team. Which type of document do you now need, among others, to better understand and then be able to improve the situation?

  1. Project charter

  2. Team performance assessments

  3. Cost baseline

  4. Statement of work

The correct answer is: Team performance assessments

Team performance assessments are the best type of document to understand and address a negative attitude within the team. A project charter outlines the key aspects of a project, such as objectives and scope, but it does not focus specifically on team dynamics or attitudes. A cost baseline only looks at project expenses and budget, which may not directly address team performance. A statement of work details project activities, but does not provide insight into team attitudes. Therefore, the most appropriate document to address and improve a negative attitude within a team is a team performance assessment, which can identify areas of improvement and allow for targeted interventions.