Project Management Professional (PMP) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Study for the Project Management Professional (PMP) exam. Study with flashcards and multiple choice questions. With over 500 questions. Practice the PMP practice multiple choice questions. Updated for 2023-2025. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


You are going to take over a new project as the project manager in an enterprise unknown to you. What should you investigate during the chartering process?

  1. Enterprise environmental factors

  2. Project management plan

  3. Project risk register

  4. Team performance reports

The correct answer is: Enterprise environmental factors

When taking over a new project, it's important to investigate the Enterprise Environmental Factors during the chartering process. Enterprise Environmental Factors are external influences that can impact a project, such as industry standards, organizational culture, and market conditions. By understanding these factors, a project manager can better anticipate potential challenges and make informed decisions to ensure project success. Project Management Plan, Project Risk Register, and Team Performance Reports are all important project documents but they are more relevant to the executing and monitoring phases of a project, rather than the initial chartering process. Therefore, they are incorrect options for this question.