You are identifying key stakeholders for your project. Which of the following groups is least likely to be included?

  1. Project manager and project team

  2. Customer and users

  3. Sponsor

  4. Media representatives

The correct answer is: Media representatives

Project managers and project team members are included because they are responsible for planning and executing the project. Customers and users are included because they are directly impacted by the project. Sponsors are typically the ones funding the project. Media representatives, while they may be interested in the project, would not typically be directly impacted by it and therefore would be least likely to be included as key stakeholders.